The government says it has reclaimed 1,486.21 hectares of land across the Maldives during the first three years of President Dr Mohamed Muizzu’s administration, with 11 land reclamation projects completed over the period.
According to government statistics, 1,175.90 hectares were reclaimed nationwide between 2013 and 2018, while 793.12 hectares were reclaimed during the previous Maldivian Democratic Party (MDP) administration’s five-year term.
The figures indicate that the land reclaimed during the current administration’s first three years is approximately 87 percent greater than the amount reported for the preceding five-year administration.
Several projects in the Greater Malé area were initiated or announced under earlier governments. At Hulhumalé Phase 3, the government said 10 hectares had been reclaimed under the previous administration, followed by an additional 53 hectares during the current administration.
At Gulhifalhu, reclamation undertaken across four previous administrations accounted for 141.70 hectares. The current administration reports having added another 64.30 hectares, while work continues to reclaim a further 85 hectares.
The government has also completed the remaining 62 hectares of reclamation at Giraavaru Falhu, part of a project covering a designated 167 hectares.
Meanwhile, 727.43 hectares have been reclaimed under the Rasmalé development project, according to the figures, with an additional 281.57 hectares still being worked on.
Overall, the government reports that approximately 907 hectares have been added to the landmass of the Malé region during the past three years. It says this figure alone exceeds the 793.12 hectares reclaimed nationwide during the previous MDP administration.
Beyond the completed works, 34 reclamation projects are currently underway on islands across the country, while another 46 projects are planned, according to the government’s figures.
To increase the pace and capacity of future reclamation work, the government has decided to acquire a new dredger for Maldives Transport and Contracting Company (MTCC). The proposed vessel is expected to be several times larger than MTCC’s existing Mahaa dredger.
The figures reflect the government’s account of progress on land reclamation projects. The supplied statistics do not include an independent assessment of project costs, environmental impacts or completion schedules for the remaining works.