225 projects across 20 atolls: what MTCC’s project map shows

Maldives Ledger graphic: 225 projects across all 20 atolls on MTCC's project map; 59 ongoing, 50 idle, 44 not started. A phone on a sunlit desk shows the count.

Maldives Transport and Contracting Company (MTCC) now lists 225 infrastructure projects across all 20 administrative atolls on its public project map, a national dashboard that tracks the status and progress of its work island by island.

The projects range from harbours and land reclamation to shore protection, schools, hospitals and public buildings, many of them carried out for the Ministry of Infrastructure, Housing and Urban Development.

Where things stand

According to the map’s status counts, 153 projects are currently active or pending:

  • Ongoing: 59
  • Idle: 50
  • Not started: 44

The remaining projects on the map are listed with other statuses, such as physically completed or in their defects liability period.

Advertisement
Ads by Rome

Atolls with the most projects

Haa Alif, Kaafu and Alif Alif have the most projects listed, with 23 each, followed by Raa with 19, and Shaviyani and Gaafu Dhaalu with 15 each. Haa Alif, Noonu and Gaafu Dhaalu have the most ongoing work, with eight active projects each.

Raa and Laamu have the highest number of idle projects, with six each, followed by Alif Alif, Alif Dhaal and Shaviyani with five each.

Projects in focus

Gdh. Thinadhoo industrial zone: The land reclamation and shore protection project for an industrial zone at Thinadhoo, under a contract signed on 9 January 2022, is listed as 91 percent complete. Its scope includes 135,820 square metres of reclamation, 1,521 metres of rock shore protection, quay walls and a 15-metre bridge linking the existing island to the new land.

N. Manadhoo harbour channel: The harbour expansion at Manadhoo, including maintenance dredging, shore protection and jetty construction, is listed as 100 percent complete and in its defects liability period.

Ha. Ihavandhoo fish collection centre harbour: Awarded to MTCC on 17 August 2023, the project covers a 129-metre sheet pile quay wall, a 66-metre L-block quay wall, revetment and around 50,000 cubic metres of dredging. It is listed as idle, at 11 percent progress.

The figures are as shown on MTCC’s project map at projects.mtcc.com.mv on 18 November 2026.